Compare China supplier quotes.

A CNY 10 unit price can cost more than CNY 11. Here is why.

Worked example · fictional data, not a client project

The same order. Different quoted totals.

100 pieces of the same 24 cm matte-white stoneware vase. CNY. EXW Guangzhou. Product and protective packing only.

SupplierUnit pricePackingProduct + packing
A10.002001,200
B11.00Included1,100
C9.50Not quotedCannot compare yet

B is CNY 100 lower than A for this quoted scope. C cannot be compared yet because its packing cost is missing.

Not landed cost. Freight, duties, taxes and other unquoted costs are excluded. Price alone does not approve a supplier.

Get example + blank Excel

First tab: Worked example. Second tab: Blank template for your own project.

Discuss a supplier comparison
Matching matte-white stoneware vases with protective packing for a supplier cost comparison
AI-generated editorial illustration of vases and packing options, not the three suppliers' offers. Comparison figures are fictional teaching data.
01

Make the offers comparable first.

A lower unit price is not necessarily a lower price for the same order. A different material, quantity break, pack format or delivery scope changes what you are buying. Send the same brief to each supplier and keep deviations visible.

The fields to align before comparing prices
Worked example · fictional data

The lower unit price is not always the lower quoted cost.

100 pieces of the same 24 cm matte-white stoneware vase. CNY. EXW Guangzhou. Product and protective packing only.

Supplier A

Unit price
CNY 10
100 pieces
CNY 1,000
Packing
CNY 200
Product + packing
CNY 1,200

Supplier B

Unit price
CNY 11
100 pieces
CNY 1,100
Packing
Included
Product + packing
CNY 1,100

Supplier C

Unit price
CNY 9.5
100 pieces
CNY 950
Packing
Not quoted
Product + packing
Cannot compare yet
What this tells you

B is CNY 100 lower than A for this quoted scope. C cannot be compared yet because its packing cost is missing.

Not landed cost. Freight, duties, taxes and other unquoted costs are excluded. Price alone does not approve a supplier.

Fictional teaching example. Not a client project, supplier offer or purchasing recommendation.

Align these fields before comparing the numbers
Buying basisAsk each supplier to stateWhat can change the decision
Product & revisionModel, drawing or specification version, material and finishA cheaper alternative may not meet the same requirement.
Quantity & unitOrder quantity, unit of sale and minimum by design or colourA piece, set, carton or metre is not an interchangeable unit.
PackingRetail pack, accessories, carton quantities and protective packingExcluded packaging can change both cost and shipment size.
Currency & deliveryCurrency, delivery rule, named place and included transportFactory collection and delivery to a destination have different scopes.
One-off chargesTooling, development, setup and sample charges separatelyDo not bury one-off costs in the repeat unit price.
Timing & validitySample timing, production timing, start condition and quote validityA quoted lead time is not a booked production or delivery date.

For delivery terminology, the U.S. International Trade Administration's Incoterms overview explains why the rule and named place matter. Record the agreed scope explicitly. A delivery rule does not replace the rest of the commercial agreement.

02

Resolve the differences before ranking suppliers.

  1. 01

    Keep the original offer

    Record the supplier's actual quotation and evidence link. Put your comparison notes alongside it rather than silently changing its terms.

  2. 02

    Separate known and missing

    A confirmed zero charge is different from an unanswered question. If currencies or delivery scopes differ, resolve them before treating totals as comparable.

  3. 03

    Recommend the next decision

    Consider specification fit, samples, payment exposure, manufacturing evidence and open issues alongside price. Record why a supplier proceeds, needs clarification or is held.

03

Compare three suppliers on one sheet.

Your own project

Supplier quotation comparison

See how packing changes a price comparison, then use the blank sheet with your own supplier quotations.

Get example + blank Excel

First tab: Worked example. Second tab: Blank template for your own project.

Should I divide tooling across the first order?

Keep the original tooling charge separate first. An allocated per-unit figure can help evaluate a stated order scenario, but it should not be mistaken for a supplier's repeat unit price. Confirm ownership, change responsibility and any reuse conditions separately.

The template is a comparison aid, not a supplier rating or a recommendation to place an order. It does not assume that an empty cost cell is a confirmed zero.

Move the supplier work forward

Discuss a supplier comparison.

Bring the quotations you need compared. We will clarify the buying basis, missing costs and supplier questions with you.

Discuss a supplier comparison